Sunday, November 21, 2021
Polar Express
Thursday, October 7, 2021
Bucksport Progress Report
Friday, October 1, 2021
New Control Panels
In both cases the bleed over from white paint into the black was not acceptable and the new panel just didn't look right.
It would be easier in the long run to re-make the paper mill panel and change some of the holes around for a better layout and then re-paint the other one.
As of this afternoon the new panels were much better and I can start installing them tomorrow. Then once that is done (and programming to the computer) I will have full local control, which will make testing and ops much easier.
Tuesday, September 28, 2021
On To The Control Panels
I have advanced to working on the design for the control panel for the paper mill. Size wise it will come from the old Portland panel, it will be a little tight, but doable. Tomorrow I will start the panel building process. This will take a few days from start to finish.
Monday, September 27, 2021
Powering up the Paper Mill
What this means so far is that the paper mill can act as a four track staging yard as far as testing is concerned. It gives me staging at two ends and a yard in the middle. A good chance to move cars and check track work.
That being said, I still need to get a local control panel to make turnouts easier to use.
Thursday, September 23, 2021
Paper Mill Progress
The paper mill track work is 95% complete. Power will come next. For those of you that saw the last layout. There is more space and a few more spots than the last time. Included this time is a smal yard for storage. We might even be able to have a full time operator at the mill.
The first picture shows the mainline from the south. You will see the yard lead and the power plant.
Then you come upon the warehouse and the south end of the yard. Along with the Main and passing siding.
Now you see the Kraft Mill and the tank dock after that.
Next you will see the double tracks for the pulpwood and wood chips. There is also a short track to hold and engine and a caboose.
Thursday, September 16, 2021
Paper Mill going in
Now the paper mill has its plan developed and currently the south end is being put in place.
This go round the complex will have roughly the same amount of spots. They will be a little more spread out than the last time and this time there will be a small yard with a lead so the work can stay of of the main.
Friday, July 23, 2021
Benchwork Additions
Tuesday, June 22, 2021
Area Op Sessions
Wednesday, June 16, 2021
Rough ideas
The first idea was a long central peninsula with the main yard on the peninsula.
Finally some action
In the meantime I just put together some pieces for the center peninsula for sizing purposes. One side is 24" deep and the other is 31 1/2" deep. A 2 x 4 will go between them for a backdrop. Currently the middle has 16' of length. This leaves me with an aisle of 37" and the other is 43". The wider side was for the yard area. Since then I have another idea to check out for benchwork location, so the aisles could be equalized.
Yes, the kayak will have its new location tomorrow.
Monday, April 12, 2021
Train Room Update
Friday, April 9, 2021
RR update
Thursday, April 1, 2021
Wall preps
Monday, March 29, 2021
More land aquired
Friday, March 19, 2021
Lights
Thursday, March 4, 2021
More lights
Wednesday, March 3, 2021
Let there be light
Saturday, February 27, 2021
Backdrop started around Searsport
The right side of Searsport
The left side of Searsport
The exit of Searsport to the north.
Wednesday, February 24, 2021
Switch lists or Car Cards
Friday, February 19, 2021
Rolling Stock Update
Monday, February 15, 2021
Not much going on
I adjusted the helix so that the track had a slight elevation on the outside rail. I had one spot that dipped the wrong way and it took a shim to fix that. Then I was derailing at a joint. It took a bit of soldering to get things right and now it appears that I am ok (for now).
Tuesday, January 26, 2021
8 foot Extension complete
The extension to include the north side of Searsport (top) and Wiscasset is complete. This includes all of the track and computer connections. It also includes a temporary control panel. Only the left side works because that is all I need for now
The left side of the new section. Of course I forgot to put in all the buildings.
The right side of the eight foot section.
The next section will include the rest of Wiscasset.
Saturday, January 23, 2021
Electrical and Electronic Day for Wiscasset
Chuck
Friday, January 22, 2021
Thursday, January 21, 2021
Wiscasset
Track Photos
Below is the nine track staging yard for St. Albans
Below is the helix to get you out of St. Albans. Three turns gets you to the wye so you can head for Portland. The last turn gets you up to Searsport and the direction of Bangor.
Below is the wye at Belfast.
Wednesday, January 20, 2021
Train room dimensions
Searsport has an actual arrival and departure track and the yard lead can pull a whole track at once. Also the sidings are much longer.
Saturday, January 16, 2021
Anyone still out here?
I will be starting this blog back up, if anyone is still interested. I had been on Facebook for a while and now I left there and will start back on here. Since the last time the layout was torn down for a move and now I am restarting in a new location.
Let me know if you see this post.